Sign In

Major Projects

​​​​​The following major projects are scheduled for completion within King Township in 2017 - 2020:

 

​Nobleton sanitary sewer works (I & I)


Township contract forces will be undertaking various sanitary sewer works in the north-east area of Nobleton.​

Public Notice

Project Update Report-November 09, 2018​

​​

Nobleton Phase 2 Sanitary Sewer Construction

Public Open House - Wednesday, May 30, 2018
Nobleton Arena - 15 Old King Road
Seniors Room 5:00 pm - 7:00 pm

Sanitary Sewer Contract Area Map

Public Open House, Wednesday, December 6, 2017
Estimated Completion End of 2018

Public Open House - Draft Financial Options

Public Open House - PIC Drawings

Engineering & Public Works Department​
​Sanitary Sewer Construction

Construction Notice - November 2018​

Construction Update - October 2018 

Construction Update - September 2018

Construction Update - August 2018

Update on Construction Notice - July 2018

JR-2017-03 "Schedule A"
Consultants Property Information Sheet

Western Avenue and King Road Watermain Re-lining

Works Update Number 3​

​Beginning: August 07, 2018

Estimated Completion: November 30, 2018

​​
Works has been substantially completed on this Project with final restoration works outstanding. Some restoration works may have to wait until spring.

Engineering, Public Works and Building Department
Environmental Project Manager:
John Vandenberg, C. Tech, WQA, EP
jvandenberg@king.ca​

​Collard Drive Sanitary Pumping Station
(SPS) Upgrades

Beginning:  Late July, 2018
Expected Completion:  Late September, 2018

​Engineering & Public Works Department

Collard Drive SPS Upgrades​

Notice to Residents

Project Status Update​

Collard Drive Closure

​Street Light Conversion Program

Crews will begin replacing 2,000 street lights in King City, followed by Nobleton and Schomberg.


​Beginning: Monday, April 23rd, 2018
Expected Completion: Ongoing

Road Reconstruction Projects:

15th Sideroad - 10th Concession to Highway 27. Public Open House: November 28, 2018     Construction: Estimated 2019 / 2020

15th Sideroad - Highway 27 to 8th Concession.  Public Open House: Wednesday, March 15, 2018.     Construction: Estimated 2019 

10th Concession - King Road to 15th Sideroad.
Public Open House: November 28, 2018
Construction: Estimated 2019 / 2020

8th Concession - 15th Sideroad to King Road.
Public Open House: November 28, 2018
Construction: Estimated 2022 / 2023

​​Road Construction
Engineering & Public Works Department

Notice to Residents Re: Open House November 28, 2018, 5:30 to 7:30 p.m., Nobleton Community Hall
 

Notice to Residents Re: Open House March 15th, 2018


​Ministry of Transportation Highway 400 Lane Expansion Project (King and Vaughan Area)
Contract # 2017-2001

Beginning: June, 2017
Estimated Completion: September, 2020


 

​Road Reconstruction and urbanization
Ministry of Transportation
1-800-268-4686

 

​